Straight answers from a builder in North London.

The builder has walked off site. What do I actually do?

Tell us what has been built, what the quote says and what you have paid. We pass it to a builder who works across London and the Home Counties, so you can ask what it would take to finish.

Key information

  • If any part of the price went on a credit card, even just the deposit, Section 75 may help. It covers an item priced over £100 and up to £30,000.
  • Check Companies House before you assume he is bust. It is free and takes one minute.
  • Make the building safe and watertight first. It is usually cheap, it is urgent, and it commits you to nothing.
  • Do not get another builder to finish the work before you open a trade body file. That order closes the free routes.
  • You have six years to bring a contract claim. Almost nothing here has to be decided this week.
The Brent Cross West station site during construction, with hoardings, bare ground and a steel frame beyond.
The Brent Cross West station site during construction in 2021. Photo: Bellowhead678 (CC BY-SA 4.0)
First step
Free enquiry
Reply time
We reply by email, usually within one working day.
Who answers
Richard Sacks, Project Squared Construction
Patch
NW, N, HA, EN, WD and around

The three questions people arrive with

Verdict first, reasoning second. If you are on a phone late at night, the first line of each card is the answer.

Has he taken my money?

Usually not, and there is a tell. The commonest pattern by a long way is a builder using your stage payment to close out someone else's job, meaning to come back. From inside the house that feels identical to being robbed. Look at whether his tools, plant, scaffold or unopened materials are still on your site. A builder who has decided never to return collects his gear first.

How much have I lost?

Almost certainly less than the number in your head. The question is not how much you have paid, it is how much value is standing in your house. Foundations, drainage, a steel, first fix wiring, a new roof structure: all real value already delivered, and all of it looks like nothing. Put what you paid in one column and what is physically in place in the other before you do anything else. It usually changes what the problem is.

What will it cost to finish?

It depends on what is already there. Get that written down first. Nobody can price the finish until someone has looked at what is there. Project Squared Construction advises a schedule of works, drawn up by an architect, so that every builder prices the same list. Have the part-built work inspected first. Then ask for quotes against that list.

Warning signs worth checking now

Things you can look at in the next five minutes, with no tools.

Look up the company at Companies House

Type the name on the invoice into the Companies House register. Read the status line: Active, Active proposal to strike off, Liquidation, or Dissolved. It is free and it takes two minutes. Most of the time it says Active, which means the problem is behaviour, and behaviour responds to a letter.

Add up what you paid against the stages you agreed

One sheet, two columns. Paid on the left, delivered on the right. Most people find the gap is smaller, or a completely different shape, from the one they have been carrying around.

Walk the site and look for his property

Tools, plant, scaffold, a skip, unopened materials. Anything of his still on site is both a reason for him to come back and a sign that he intends to.

Check how you paid

Any part of it on a credit card may bring the contract into Section 75 scope if the price is over £100 and no more than £30,000. A debit card means a chargeback clock of roughly 120 days is already running. Bank transfer or cash means neither, so the route is different.

Find out if the work was notified to building control

Look for a building notice or full plans reference on any paperwork, or ring the council's building control team. If notifiable work was never notified, that is a separate problem to solve whatever happens with the builder.

Check the trade body logo is real

If he claimed Federation of Master Builders or TrustMark membership, check it on their own site. A current member means a free dispute route exists. A logo he was not entitled to use is evidence.

If more than one of these sounds familiar, tell us what you can see.

Why this happens

Most cases come down to a short list. The job is to work out which, and to rule out the ones that matter.

Cash flow

He used your stage payment to close out another job and is now waiting on a payment elsewhere before he can come back to yours. In our experience this is the single commonest reason a site goes quiet.

What to do: Put a written deadline on it. A cash-flow builder normally responds to a firm date, because he wants the rest of your money.

Two jobs collided

He took work that was meant to run in sequence, one of them overran, and now both clients are ringing him. Nothing sinister, badly managed.

What to do: Ask for a written programme with dates rather than an apology. If he cannot give you dates, he does not have them.

He priced it too low

The job is now losing him money, usually because of unpriced variations, something found in the ground, or material prices moving. The silence is avoidance of a conversation he does not want to have.

What to do: Get the conversation happening on paper. Sometimes a fair renegotiation of a genuinely mispriced item is cheaper than replacing him.

There is a live argument about money

An unresolved disagreement about a variation or a stage payment, with absence being used as leverage. Both sides usually think they are the reasonable one.

What to do: Write down the disputed item and your figure for it. A specific number is much harder to ignore than a general complaint.

He is waiting on materials or a subcontractor

Steel, windows, a structural engineer's detail, a groundworker. He goes quiet rather than admit he has no date to give you.

What to do: Ask which supplier and which order number. A real delay has a reference. An invented one does not.

Illness, injury or a family crisis

Common, under-reported, and invisible from your side of the fence, because a small builder has no cover and often no one to make the call for him.

What to do: Worth one text asking if he is all right before you escalate. It costs nothing and it occasionally explains everything.

What happens next, cheapest first

We scale the response to the problem. Most enquiries do not need the bigger step, and we will tell you if yours does not.

  1. Free enquiry

    Tell us what has been built, what is left and what you have paid. We pass it to Project Squared Construction, who can say whether they can look at it.

    CostFree TimeWe aim to pass it on the same working day

  2. Make it safe and watertight

    An open roof, an exposed steel, a trench in the garden. If any part looks dangerous, keep out and tell the council at once, even out of hours. Getting the building weathertight is a separate small job that commits you to nothing about the dispute.

    CostQuoted on what is exposed. Keep the invoice and photographs TimeStraight away if anything is unsafe

  3. An independent survey and a written scope to finish

    Someone with no stake in the argument lists what is in place, what is defective and what it takes to complete. It stops you paying to redo work that is perfectly sound, and it is the document that makes another builder willing to quote.

    CostAsk for a fixed fee in writing before you instruct TimeAsk for the report date when you book

Things that are usually fine

Straight from Richard, who would rather tell you now than charge you later.

A builder who stops turning up has not always run off with your money. Keep a dated record and ask in writing for a return date before you assume the worst.

Richard Sacks, Project Squared Construction

Silence on its own does not prove a builder has walked away. Ask in writing for a return date and note whether the tools and scaffold are still there.

Richard Sacks, Project Squared Construction

Part-built work does not always need ripping out. An independent inspection lists what is sound, what is defective and what it would take to finish.

Richard Sacks, Project Squared Construction

Builder: who to call

How we choose.

Recommended

Referred by other local business owners we work alongside. Not an editorial review.

Show 3 other businesses serving Hendon

Also serving Hendon

Local businesses checked against public sources: their own websites and the public registers.

LCCL Construction

Based in Finchley. Covers Hendon, Mill Hill, Finchley and Barnet.

Design and build firm in Finchley for loft conversions, house extensions, renovations, basements and new builds across north London.

Milkov & Son Construction

Based in Hendon. Covers Hendon, Finchley, Mill Hill, Barnet, Hampstead Garden Suburb and Edgware.

Family design and build firm based in Hendon for house extensions, loft and basement conversions, full renovations and new homes.

Protostar Construction

Based in Golders Green. Covers Hendon, Golders Green, Mill Hill, Finchley, Colindale and Edgware.

Residential building firm in Golders Green for house extensions, loft conversions and refurbishments across north London.

Tiers reflect membership of business groups we work alongside, not paid placement. Nobody pays to be listed.

Sometimes this is really a job for a different trade. We also refer to architect and roofer, and we say so when it is.

Questions people ask

How long before it counts as abandonment?
There is no fixed number of days in law, and that is the honest answer. What changes the position is a written deadline. Put in writing what you need done, by when, and say what you will do if it is not. Until you have done that, a court or a mediator has nothing to look at.
Can I get my whole deposit back?
Usually not, and demanding it damages your position. If materials were ordered, scaffold erected or site set-up done, he is entitled to be paid for that. The claim that gets paid is the narrower one: the amount you paid in advance for work not done. Ask for the right figure and you are far more likely to get it.
I paid the deposit on a credit card. Does that help?
It may help a great deal. Under Section 75 of the Consumer Credit Act the card issuer can be jointly liable with the builder. You only had to put part of the price on the card. It covers an item priced over £100 and up to £30,000, so a larger building contract may fall outside it. It does not apply to debit cards, which go through chargeback instead, with a window of roughly 120 days.
How do I know if he has gone bust?
Search the company name on the Companies House register. It is free and instant. People assume insolvency because they cannot get hold of someone, and most of the time the company is simply Active with nothing filed. If it is a limited company, the claim is against the company, not the director personally, and a dissolved company has to be restored to the register before it can be sued at all.
He is asking for more money. Is that a scam?
Not automatically. There is a real and common case where he is skint and has an unpaid merchant account, so he cannot get materials. The test is whether he will let you pay the merchant directly on your own card instead of paying him. A struggling builder usually takes that deal because it solves his problem. Someone who insists the money comes to him personally, in cash, before anything happens, is telling you something.
Should I just get another builder in to finish it?
Yes, but not before you open the file. The Federation of Master Builders will not assist once the work has been completed by another builder, and TrustMark cannot act once legal action has started or the business has ceased trading. Start the free route first, even if you do not think you will use it.
What happens about building control sign-off?
Abandoned notifiable work can usually be regularised. The process exists in law for exactly this, for anything done since 11 November 1985. The council will normally want areas opened up for inspection, which is inconvenient and costs money, but it is a defined process with a defined end. The enforcement window is 10 years from completion, not the 12 months a lot of older advice still says, which means there is time to do it properly.
How long does a court claim take?
Longer than people expect. The published median from issuing a claim to a small claims trial is 41 weeks. Before that there is compulsory free mediation for defended claims up to £10,000, which is one telephone appointment and is where most of these actually settle. The small claims track is the normal track for claims up to £10,000, and it is a track within the County Court, not a separate court.
Do you cover Hendon and Mill Hill?
Yes. Hendon, Mill Hill, Finchley, Edgware, Golders Green, Colindale and Barnet are our core patch, with members across North London and Hertfordshire.
What if I am outside North London?
Tell us the postcode. If nobody we recommend covers your area we will tell you.

Further reading: Make a court claim for money (GOV.UK), Federation of Master Builders: dispute resolution and Consumer Rights Act 2015, section 54: your rights when a service goes wrong.

Where we cover

Hendon, Mill Hill, Finchley, Edgware, Golders Green, Colindale, Barnet and the rest of North London and Hertfordshire. If you are outside this area, tell us where you are and we will point you to someone who covers you.

Not sure whether it is anything?

Tell us what has happened and your postcode. We tell you whether it needs anyone and what to do next. We reply by email, usually within one working day.